Nova Scotia Power estimates scaled-down version of Atlantic Loop to cost $700 million
The current estimate for what has become known as a scaled-down version of the Atlantic Loop electrical grid project is about $700 million, the head of Nova Scotia's private power utility said Tuesday.
Talks continue on how to finance a power line that would run parallel to an existing connection between Onslow, N.S., and Salisbury, N.B., Nova Scotia Power CEO Peter Gregg told the province's natural resources committee. The line, he said, would help carry power from future renewable energy projects between Nova Scotia and New Brunswick.
The project is considered a key element of Nova Scotia's plan to close its coal plants and get 80 per cent of its energy from renewable sources by 2030.
But Gregg said the project is part of a larger puzzle that includes energy from renewable wind, solar and battery projects as well as continued imports of hydroelectricity from Labrador through the existing Maritime Link.
"It's going to take a portfolio of solutions to allow us to get off coal," he said. "You shouldn't look at it as one investment that will allow us to get off coal, it needs to all work together to do that."
Gregg said the 345-kilovolt power line project, often referred to as the "intertie," received environmental approval late last year and detailed engineering studies are underway.
"We are continuing to work with the federal government and the Canada Infrastructure Bank on how to financially structure the project final details haven't been worked out," he said.
Gregg later told reporters the total cost could double to $1.4 billion if the power line eventually runs west to Point Lepreau, N.B., as planned. He said he was confident the scaled-down project can be delivered on time, although he couldn't give an exact date when construction would begin.
"It's either 2027 or 2028," he said. "It's a critical project that will allow us to add about 1,000 megawatts of wind (power) to the system."
Last fall, Nova Scotia said it would be too expensive to take part in the original Atlantic Loop proposal, a grid project that would have transferred hydroelectricity to the province from Quebec and Newfoundland and Labrador. The government had said capital cost estimates had tripled to more than $9 billion, and Quebec had become reluctant to divert its hydro from other priorities.
Karen Gatien, deputy minister of natural resources, told the committee that the province's energy goals beyond 2030 might need an expanded project similar to the original Atlantic Loop.
"We still need to reach net zero by 2050 and (an expanded loop) just might help us get there," said Gatien. "But there are many other pieces of our plan that are essential for reaching 2030. Pieces we need to do regardless of the loop."
This report by The Canadian Press was first published April, 23, 2024.
For more Nova Scotia news visit our dedicated provincial page.
CTVNews.ca Top Stories
BREAKING Foreign meddling 'did not affect' overall federal election results: inquiry report
Foreign interference by China did not affect the overall results of the 2019 and 2021 general elections won by Justin Trudeau's Liberals, a federal commission of inquiry has found.
BREAKING Police arrest 3 in killing of B.C. Sikh activist Hardeep Singh Nijjar
Three people have been arrested and charged in the killing of B.C. Sikh activist Hardeep Singh Nijjar.
Why your airfare may be getting more expensive
Skyrocketing airfare prices are linked to heightened competition and rising food and fuel, according to the CAA.
WATCH LIVE Funeral today for broadcasting legend and voice of 'Hockey Night in Canada' Bob Cole
A funeral is being held today for hockey broadcasting legend Bob Cole in his hometown of St. John's, N.L.
Magnitude 4.8 earthquake recorded west of Vancouver Island
A 4.8-magnitude earthquake was reported west of Vancouver Island Thursday evening.
Who is Hope Hicks, longtime Trump aide who is testifying in N.Y. hush money case?
Hope Hicks, once a longtime trusted aide in Donald Trump’s inner circle, is testifying Friday in the New York hush money trial after being subpoenaed.
TD worst-case scenario more likely after drug money laundering allegations: analyst
TD Bank Group could be hit with more severe penalties than previously expected, says a banking analyst after a report that the investigation it faces in the U.S. is tied to laundering illicit fentanyl profits.
Police officer hit by driver of fleeing vehicle in Toronto incident caught on video
York Regional Police say they are continuing to search for a suspect in an auto theft investigation who was captured on video running over a police officer in Toronto last month.
How falling for a stranger she met on a beach led this woman to ditch the U.S. for the French Riviera
Niki Benjamin, from the U.S., had travelled to a paradise island to do some soul searching, and her life ended up going in a very different direction when her dog ran up to a stranger.