Fundy Quay project underway at Saint John waterfront
A large section of the uptown Saint John waterfront has become a construction zone, with site preparation work for both, private and public portions of the high-profile Fundy Quay project taking place.
"The sea wall construction is well underway, it’s approximately 75-percent complete, slightly ahead of schedule," says Brent McGovern, the city’s commissioner of utilities and infrastructure for the City of Saint John.
"We also have the demolition work that’s also underway and slightly ahead of schedule."
The project by the Fundy Harbour Group is a mixed-use development that will see the construction of five buildings, which will include over 600 residential units.
The director of growth for Envision Saint John, Jeffrey Cyr, says that residents and visitors could soon see construction on a 16-storey building in the southeast corner of the Fundy Quay site.
"With commercial on the ground floor, parking towards the centre of the building," says Cyr. "That project is anticipated to begin when we turn the site over to [the developer] and that’s scheduled for July of this year."
Happening alongside the Fundy Quay project is the city’s redesign of Market Slip. The transformation will include added greenery space, an amphitheater, enhanced performance stage, and a feature called the Tidal Steps.
McGovern says a tender for the design work for the public space will be released for bidding over the next month.
The city says as well that an interim patio season will be taking place starting in June and extending to the fall.
Restaurant owner, Corey McGill, says the construction has had an impact on his business, and they’ve been working to get the word out that they are open.
"We are still operating and that we are looking forward to operating our temporary patios for this season," says McGill.
"The big thing for our end is we’re pretty excited for this transformation down on the boardwalk, it’s been coming for a long time."
The public spaces at Market Slip are anticipated to be completed in 2023.
The Fundy Quay project is expected to be an eight to 10 year process for full build out.
CTVNews.ca Top Stories
More than 115 cases of eye damage reported in Ontario after solar eclipse
More than 115 people who viewed the solar eclipse in Ontario earlier this month experienced eye damage after the event, according to eye doctors in the province.
Toxic testing standoff: Family leaves house over air quality
A Sherwood Park family says their new house is uninhabitable. The McNaughton's say they were forced to leave the house after living there for only a week because contaminants inside made it difficult to breathe.
Decoy bear used to catch man who illegally killed a grizzly, B.C. conservation officers say
A man has been handed a lengthy hunting ban and fined thousands of dollars for illegally killing a grizzly bear, B.C. conservation officers say.
B.C. seeks ban on public drug use, dialing back decriminalization
The B.C. NDP has asked the federal government to recriminalize public drug use, marking a major shift in the province's approach to addressing the deadly overdose crisis.
OPP responds to apparent video of officer supporting anti-Trudeau government protestors
The Ontario Provincial Police (OPP) says it's investigating an interaction between a uniformed officer and anti-Trudeau government protestors after a video circulated on social media.
An emergency slide falls off a Delta Air Lines plane, forcing pilots to return to JFK in New York
An emergency slide fell off a Delta Air Lines jetliner shortly after takeoff Friday from New York, and pilots who felt a vibration in the plane circled back to land safely at JFK Airport.
Sophie Gregoire Trudeau on navigating post-political life, co-parenting and freedom
Sophie Gregoire Trudeau says there is 'still so much love' between her and Prime Minister Justin Trudeau, as they navigate their post-separation relationship co-parenting their three children.
Last letters of pioneering climber who died on Everest reveal dark side of mountaineering
George Mallory is renowned for being one of the first British mountaineers to attempt to scale the dizzying heights of Mount Everest during the 1920s. Nearly a century later, newly digitized letters shed light on Mallory’s hopes and fears about ascending Everest.
Loud boom in Hamilton caused by propane tank, police say
A loud explosion was heard across Hamilton on Friday after a propane tank was accidentally destroyed and detonated at a local scrap metal yard, police say.