Nova Scotia Power estimates scaled-down version of Atlantic Loop to cost $700 million
The current estimate for what has become known as a scaled-down version of the Atlantic Loop electrical grid project is about $700 million, the head of Nova Scotia's private power utility said Tuesday.
Talks continue on how to finance a power line that would run parallel to an existing connection between Onslow, N.S., and Salisbury, N.B., Nova Scotia Power CEO Peter Gregg told the province's natural resources committee. The line, he said, would help carry power from future renewable energy projects between Nova Scotia and New Brunswick.
The project is considered a key element of Nova Scotia's plan to close its coal plants and get 80 per cent of its energy from renewable sources by 2030.
But Gregg said the project is part of a larger puzzle that includes energy from renewable wind, solar and battery projects as well as continued imports of hydroelectricity from Labrador through the existing Maritime Link.
"It's going to take a portfolio of solutions to allow us to get off coal," he said. "You shouldn't look at it as one investment that will allow us to get off coal, it needs to all work together to do that."
Gregg said the 345-kilovolt power line project, often referred to as the "intertie," received environmental approval late last year and detailed engineering studies are underway.
"We are continuing to work with the federal government and the Canada Infrastructure Bank on how to financially structure the project final details haven't been worked out," he said.
Gregg later told reporters the total cost could double to $1.4 billion if the power line eventually runs west to Point Lepreau, N.B., as planned. He said he was confident the scaled-down project can be delivered on time, although he couldn't give an exact date when construction would begin.
"It's either 2027 or 2028," he said. "It's a critical project that will allow us to add about 1,000 megawatts of wind (power) to the system."
Last fall, Nova Scotia said it would be too expensive to take part in the original Atlantic Loop proposal, a grid project that would have transferred hydroelectricity to the province from Quebec and Newfoundland and Labrador. The government had said capital cost estimates had tripled to more than $9 billion, and Quebec had become reluctant to divert its hydro from other priorities.
Karen Gatien, deputy minister of natural resources, told the committee that the province's energy goals beyond 2030 might need an expanded project similar to the original Atlantic Loop.
"We still need to reach net zero by 2050 and (an expanded loop) just might help us get there," said Gatien. "But there are many other pieces of our plan that are essential for reaching 2030. Pieces we need to do regardless of the loop."
This report by The Canadian Press was first published April, 23, 2024.
For more Nova Scotia news visit our dedicated provincial page.
CTVNews.ca Top Stories
Celine Dion delivers stirring comeback performance at Paris Olympics opening ceremony
Against the rainy Paris night sky, Celine Dion staged the comeback of her career with a powerful performance from the Eiffel Tower to open the Olympic Games.
Jasper wildfire: 'Several weeks' before residents can return, premier says
Premier Danielle Smith said Friday afternoon in Hinton while weather conditions are cooler, the Jasper fire is still considered out of control and that Jasper residents can expect to be away from their homes 'for several weeks.'
Missing 3-year-old boy found dead in creek in Mississauga, Ont.: police
A three-year-old boy has been found dead a day after he went missing in a park in Mississauga, Ont., Peel police say.
Irish museum pulls Sinead O'Connor waxwork after just one day due to backlash
An Irish museum will withdraw a waxwork of singer-songwriter Sinéad O'Connor just one day after installing it, following a backlash from her family and the public, it told CNN in a statement on Friday.
Winnipeg senior's account overdrawn for $146,000 water bill
A Winnipeg senior is getting soaked with a six-figure water bill.
FBI says Trump was indeed struck by bullet during assassination attempt
Nearly two weeks after Donald Trump’s near assassination, the FBI confirmed Friday that it was indeed a bullet that struck the former president’s ear, moving to clear up conflicting accounts about what caused the former U.S. president’s injuries after a gunman opened fire at a Pennsylvania rally.
Driver charged after flashing high beams at approaching police
Orillia OPP arrested and charged a driver with impaired driving after flashing their high beams.
Turpel-Lafond won't sue CBC over Cree heritage report that took 'heavy toll': lawyer
The lawyer for a former judge whose claims to be Cree were questioned in a CBC investigation says his client is not considering legal action against the broadcaster after the Law Society of British Columbia this week backed her claims of Indigenous heritage.
Major Canadian bank experiences direct deposit outage on payday
Scotiabank says it has fixed a technical issue that impacted direct deposits on Friday morning.